A rebar takeoff is a bar-by-bar count taken from the structural drawings, converted to weight by size, and summed into tonnage. The tonnage is only as good as the laps, hooks, dowels and ties counted with it.
Who this is for: concrete and rebar contractors, estimators and general contractors bidding US concrete work who have lost margin to missed laps, dowels and stirrups.
This guide walks the takeoff the way an estimator works it: general notes first, then plans, sections and schedules, a bar bending schedule as the deliverable, and a pre-bid pass over the items missed most. The pricing section near the end gives ranges with their sources and the method behind them.
What a Rebar Takeoff Is (and What It Is Not)
A rebar takeoff answers one question: how much reinforcing steel does this structure need, bar by bar. The estimator counts every bar shown on the structural drawings, groups identical bars by mark, size and shape, works out each bar's cutting length, converts linear feet to pounds using the nominal weight for its size, and totals the result in short tons. One short ton is 2,000 lb; a metric tonne is 2,204.6 lb, so a quote of $1,000 per short ton is about $1,102 per metric tonne.
A takeoff is not an estimate: a takeoff gives you quantities and weight, while an estimate adds material pricing, fabrication, placing labor, accessories and markup, and turns those quantities into a bid price. A takeoff is also not a bar bending schedule. The schedule is the fabricator's cut list: one row per bar mark with bend shape, size, leg dimensions, quantity, cutting length and weight. The takeoff feeds the schedule, and on a well-run job the estimator builds both from the same count, so the bid and the order agree.
The concrete side of the job, slabs, footings, walls and columns, is covered in our concrete takeoff guide. The steel frame side, beams, columns and connections in Division 05, is covered in our structural steel takeoff guide.
Read the Drawings in This Order
Most bad rebar takeoffs start in the wrong place. The estimator who opens the foundation plan first has already skipped the page that controls the count. Work the set in this order.
1. Structural general notes first
The general notes hold the rules for the whole job: steel grade, cover for each exposure, the lap splice schedule, hook and bend rules, and special requirements such as epoxy coating or seismic detailing. Lap lengths, cover and hook allowances all live here, and they change the tonnage. Read the notes before you count anything.
2. Foundation plans, then framing plans
Foundation plans give you the footings, grade beams, pile caps and mats, and how many of each exist. Framing plans give you the slabs, beams, walls and columns above. Count elements first, then bars within each element: a footing schedule that says F1 occurs four times means every bar in F1 gets multiplied by four.
3. Sections and details
Sections and typical details show what the plans hide: stirrup and tie spacing, hook shapes, dowels at the base of walls and columns, and corner bars. Spacing lives on the section, not the plan.
4. The bar bending schedule, if one exists
Some structural sets include a bar bending schedule prepared by the engineer. Treat it as a cross-check, not as gospel: verify its marks against the plans and sections, and rework any row that does not match. When the schedule and the drawings disagree, the drawings govern, and the conflict goes in your discrepancy log. Our guide to resolving conflicting quantities in bid documents sets out the five-step method for this kind of conflict. If you are working from PDFs, the workflow in our quantity takeoff from PDF drawings guide applies here too.

Bar Sizes, Grades and Weights
US bars are numbered by diameter in eighths of an inch up to #8: #3 is 3/8 in, #4 is 1/2 in, #5 is 5/8 in, #6 is 3/4 in and #8 is 1 in. Sizes #9, #10, #11, #14 and #18 are set by area. Grade is yield strength, not size: ASTM A615 Grade 60 (60,000 psi) is the default on most US work, ASTM A706 is the weldable, low-alloy grade used where welding or seismic ductility is required, and Grades 40, 75, 80 and 100 also exist. Mill marks show producer, size, steel type (S for A615, W for A706) and grade.
Weight is set by diameter alone; grade does not change it. The nominal weights per ASTM A615/A615M are the numbers this guide uses: a 20 ft stick of #4 weighs 13.4 lb, the same stick of #5 weighs 20.9 lb. Mill-run weight may vary within the standard tolerance.
| Bar size | Diameter (in) | Area (sq in) | Weight (lb/ft) |
|---|---|---|---|
| #3 | 0.375 | 0.11 | 0.376 |
| #4 | 0.500 | 0.20 | 0.668 |
| #5 | 0.625 | 0.31 | 1.043 |
| #6 | 0.750 | 0.44 | 1.502 |
| #7 | 0.875 | 0.60 | 2.044 |
| #8 | 1.000 | 0.79 | 2.670 |
| #9 | 1.128 | 1.00 | 3.400 |
| #10 | 1.270 | 1.27 | 4.303 |
| #11 | 1.410 | 1.56 | 5.313 |
The shortcut: weight in lb/ft equals the bar number squared times 0.668, divided by 16. A #6 bar gives 36 times 0.668 divided by 16, which is 1.502 lb/ft.
Worked Example: A Hypothetical Footing
The example below is a clearly labelled hypothetical, built to show the arithmetic, not a real project. It excludes laps, hooks, dowels and waste, which must be added from the drawings before the number means anything.
Take a 30 ft strip footing with 4 longitudinal #6 bars: 4 times 30 ft is 120 linear feet, and at 1.502 lb/ft that is 180.2 lb. The stirrups: #4 ties at 12 in on centre over 30 ft give 31 ties, each with a 5 ft cutting length, so 155 linear feet at 0.668 lb/ft is 103.5 lb.
Add them: 180.2 plus 103.5 is 283.7 lb, or 0.14 short ton, before laps, hooks, dowels and waste. On a real footing the lap steel alone can add a visible percentage, so this arithmetic is a starting point and never the bid number. Run the same method element by element and the tonnage builds itself from verifiable rows.
Laps, Hooks and Development Length: Where Tonnage Hides
Lap splices are the single biggest source of missed steel in rebar takeoffs, because a lap is steel that appears nowhere as a bar on the plan. It exists only as a length rule in the general notes, and it must be long enough to develop the bar's full design stress through bond with the concrete. The length comes from the drawings and the engineer of record, never from a rule of thumb. Do not bid off a universal '40 bar diameters' lap rule: rules of thumb ignore grade, top-bar position, coatings and concrete strength.
Under ACI 318, the reference most US jurisdictions adopt is ACI 318-19. ACI CODE-318-25 is the latest published edition (released end of January 2025, printed July 9, 2025, expected to be adopted by the 2027 IBC), but it is not the adopted edition in most jurisdictions today. Confirm the adopted edition from the project jurisdiction and specifications.
The splice rules to carry on your takeoff sheet: a Class B splice, 1.3 times the development length, is the default on most jobs. A Class A splice, 1.0 times the development length, applies only where the steel provided is at least twice what the design needs and no more than 50 percent of the bars are spliced at the same location. The minimum lap is 12 in. Bars larger than #11 must not be lap spliced under ACI 318-19 section 25.5.1.1; #14 and #18 bars use mechanical couplers or welding. Development length grows with top-bar position (more than 12 in of fresh concrete below the bar, factor 1.3), epoxy coating, higher grade (ACI 318-19 added a grade factor critical for Grade 80 and 100 bars) and lower concrete strength. Lap locations belong to the engineer of record: check the general notes and the lap schedule, and RFI anything not shown.
Hooks and bends add steel the same way: a standard hook adds length to the cutting length, and bend deductions reduce it, per the standard used. ACI/ASTM publishes no cut-length rounding, while other standards round, so state which standard your lengths follow.
The Pre-Bid Miss List: Eight Items to Check Before You Submit
Run this pass over your takeoff the day before the bid goes out. Each item is steel estimators have missed on real jobs, cheap to catch at the desk and expensive to catch in the field.
- Lap splices not counted. Calculate lap steel from the drawings and the lap schedule, never as a blanket waste percentage.
- Hooks and bend deductions. Hooks add length, bends deduct it, per the sections and the standard used.
- Dowels at footings, walls and columns. Starter bars and dowels at every concrete-to-concrete interface, counted from the details.
- Corner bars and opening trim bars. Wall corners, slab openings and penetrations carry extra bars that never appear on the plan count.
- Stirrups, ties and hoops at the spacing on the sections, not the plan. The section governs spacing: count from it, and check spacing changes at supports and openings.
- Chairs, dobies and supports for cover. Bar chairs, dobies and bolsters, counted by spacing and layout, not guessed.
- Epoxy-coated or galvanized bars priced as black bar. Coated bar costs more per ton and needs longer laps.
- The top-bar lap where the top mat sits under deep concrete. Top bars under more than 12 in of fresh concrete carry a 1.3 development-length factor.
Building the Bar Bending Schedule
The bar bending schedule is the deliverable that turns a takeoff into an order: one row per bar mark, with bend shape, size, leg dimensions, quantity, cutting length and weight. The mark ties the plan to the schedule, and the schedule row gives the bar's diameter, shape and dimensions. Build it with one row per bar set, never one row per element, so every row can be checked on its own.
Work the schedule in the same order as the takeoff: element by element, mark by mark. For each mark, record size and grade, shape (straight, L-bar, U-bar or closed tie), leg dimensions, bars per element and element count, then cutting length and weight. Total the weight by size.
Waste and cutting need the same discipline as laps. Secondary sources quote a typical wastage range of 3 to 10 percent; treat it as a typical range, never as a rule. Optimize cut lengths against the stock lengths your supplier delivers, commonly 20, 40 and 60 ft sticks.

What Rebar Costs in 2027
Rebar pricing is a scope question before it is a number question: sources disagree because they measure different scopes. Material-only, fabricated and installed ranges are three different numbers, and averaging them produces a figure that matches nothing. The ranges below are attributed to their sources and years, and no 2026 figure has been relabelled as a 2027 figure.
| Scope | Range | Source |
|---|---|---|
| Material, plain Grade 60 black bar | $700 to $1,100 per short ton | Civilmath, November 6, 2026 |
| Material, broader retail range | $1,300 to $2,000 per short ton ($0.50 to $1.00 per lb) | HomeGuide, 2026 |
| Fabrication, cut and bent | Add $80 to $150 per ton | Civilmath, November 6, 2026 |
| Epoxy coating | Add $150 to $250 per ton | Civilmath, November 6, 2026 |
| Installed, Florida (material, labor, logistics) | $2,500 to $7,000 per ton | Estimator Florida, 2026 |
Two practical points sit behind those ranges. Delivery is usually a flat charge per load, so it bites hardest on small orders. Steel tracks the scrap market, so prices move month to month: always get a current local delivered quote before you bid.
How these ranges were built
| Assumption | What this guide uses |
|---|---|
| Pricing source | Published US ranges from Civilmath (November 6, 2026), HomeGuide (2026) and Estimator Florida (2026). No RSMeans figures are quoted: none were available during preparation. |
| Labor | Material-only ranges exclude placing labor. The Florida installed range includes material, labor and logistics. No placing, tying or chair labor rate is stated: no sourced rate was available. |
| Location and size | National US averages except the Florida installed range. Remote markets pay more, and small orders cost more per ton because delivery is a flat charge per load. |
| Union vs non-union | Material prices do not change with union status. Installed prices do, because placing labor rates differ by jurisdiction. |
| Overhead | Material ranges are supplier prices before contractor markup. Installed ranges include the installer's labor and logistics but not the bidder's overhead and profit. |
| Date reviewed | November 2026. Steel prices move monthly, so re-check against a current local quote before bidding. |
These are planning ranges, not quotes. Your final price depends on your drawings, bar sizes and coatings, fabricator and market. If you want a number you can bid, our pricing page lays out how we structure fees for a takeoff, and our concrete estimating services cover rebar takeoffs as part of a full Division 03 estimate.
What the Takeoff Does Not Include
A rebar takeoff covers the reinforcing steel shown on the structural drawings, with laps, hooks, dowels, ties and accessories counted from those drawings. Unless your scope statement says otherwise, it does not include placing labor, formwork, concrete, embeds, mechanical couplers or testing. Put that list in writing on every takeoff you deliver.
What to Send Your Estimator
A rebar takeoff is only as good as the set it is built from. Send the complete structural drawings, the structural general notes, the bar bending schedule if one was issued, the specifications, all addenda issued to date, and your bid date. Flag anything unusual up front: epoxy coating, Grade 80 or 100 bars, seismic detailing, post-tensioning in the same pour, or phased steel orders.
Frequently Asked Questions
How is a rebar takeoff priced, per ton or per pound?
Material is usually quoted per short ton, small quantities often per pound: the same number divided by 2,000. What matters is the scope behind the number, material only, fabricated, or installed. Compare like with like.
Do I count lap splices separately or add a waste percentage?
Count them separately, from the drawings and the lap schedule. A waste percentage covers cutting offcuts and handling loss, not laps.
What is the difference between a rebar takeoff and a bar bending schedule?
A takeoff gives you quantities and weight by size for the bid. A bar bending schedule gives the fabricator a cut list: one row per bar mark with shape, size, leg dimensions, quantity, cutting length and weight. The takeoff feeds the schedule.
Send Your Plans for a Project-Specific Rebar Estimate
Rebar is the cheapest line on a concrete bid and one of the easiest to get wrong, because the tonnage hides in laps, hooks and dowels that never appear as bars on the plan. A bar-by-bar takeoff with a bar bending schedule behind it keeps the steel honest. Send us your structural drawings and general notes and get a flat-fee quote within the hour.